RV14 Build July 12 &13

Aft Fuselage

Spent maybe 30 mins riveting together the Elevator Trim tab motor bracket, but the rest was all on the aft Fuselage. Mostly installing the rest of the systems and cables and riveting on the side skins. Im still waiting on the tools to do close quarter dimpling to fix the elevator trim motor mounting #27 holes I forgot to dimple and the #30 holes that Im going to match drill to enlarge in the second to last bulkhead since my sloppy drilling of rivets oblonged the holes.
 Trim motor bracket mounting plate.
Elevator Trim Motor

Aft Fuselage systems installed!
 Static Lines

Rudder cables and cable guides


Cleaning, etching, and priming the last parts of this kit!!
Primer

Last wipe down with rubbing alcohol before spraying!


Time to install some of these skins! I jumped ahead in the plans a little. I can't install the aft deck until i fix the holes for the second to last bulkhead and reinstall that. My buddy Matt has been coming over to work with me while he sits on call, I can't tall you how nice it is to have a helping hand!!! Thank you Matt!

1 top side skin riveted on 1 to go!

Side skins are coming on nicely, just have to rivet the second top side skin, top skin, and finish the Aft deck area!

This thing is really looking like an airplane!

Aft Fuselage 24 Man Hours!!